MTCC Mobilizes Project Sites Under Two Projects At The Islands Hinnavaru & Felivaru

Maldives Transport and Contracting Company (MTCC) is the first and longest-serving public company in the nation that have position itself as the leading civil and marine constructor in the country. In this capacity, the company undertakes multiple projects simultaneously across all parts of the Maldives. On Saturday, the company revealed via social media that they have mobilized two project sites under two separate projects – of which the details are as follows.

Harbor Development Project At Hinnavaru in Lhaviyani Atoll

This project is valued at MVR 99.52 million and is expected to be completed within 350 days. Scope of work includes reclamation operations of 3.2 hectares; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment.

Harbor Development And Reclamation Project At Felivaru In Lhaviyani Atoll

This project is anticipated to be completed in 365 days and is valued at MVR 113.39 million. Work under the project involves reclamation operations of 6 hectares; dredging operations of 229,663.36cbm; construction of a 220m quay wall; a 148m breakwater; a 270m revetment.

(Photos; MTCC)