Significant progress is evident in the B. Kamadhoo Harbor Development project, now at an impressive 78% completion rate. The project includes the finalization of jetty construction and the successful delivery of the fourth shipment of rock boulders to the site.
The extensive scope of work encompasses various crucial installations, including harbor and channel dredging, breakwater, revetment, quay wall, concrete ramps, a concrete jetty, harbor pavement, navigational aids, harbor lights, and mooring rings. Valued at MVR 51.4 million, this development signifies a substantial infrastructural enhancement for the region.