Dredging Milestone: 70% of Hulhumale Phase 3 Site Completed

A major milestone has been reached in the Hulhumale Phase 3 project, with 70% of the site now dredged. The dredging of Site A is set to conclude by the end of this week, marking a significant step forward. Following this, attention will turn to Site B. To facilitate the smooth progress of Site B's dredging, it is urged that vehicles be promptly removed from the area. The Hulhumale Phase 3 initiative, covering 63 hectares, is part of a broader development strategy aimed at alleviating the city's persistent housing challenges.