MTCC is Always at it! See the Latest Updates on Their Harbor Construction Projects

Maldives Transport and Contracting Company Plc (MTCC) is the first public company incorporated in Maldives and is presently the leading marine and land transport provider as well as the leading marine and civil constructor in the country. Living up to their reputation, the Company is simultaneously engaged in numerous marine construction work contracted to them by government authorities at the minute where significant progress has been reported from time to time. Here is a quick look at some of the latest updates on their harbor construction projects.

Design and Construction of Harbor at Dharanboodhoo in Faafu Atoll

This project was mobilized on 27th May 2020. At the moment, work is underway on the dredging required of which 81% has already been completed. This marks 25% of overall completion of the project.

Design and Construction of Harbor at Rakeedhoo in Vaavu Atoll

58% of the overall project has been completed whereas the builders from the Company are engaged in the work of the cast in-situ wall and top slab casting capping works at present. 66% of the cast in-situ wall has been completed whereas 40% of the top slab casting capping works has been completed.

Design and Construction of Harbor at Veyvah at Meemu Atoll

As per MTCC, the ongoing work under the project is the installation of the precast concrete blocks required for the quay well construction which is 66% completed as of right now. 45% of the overall project is marked complete.