STELCO Energizes Voltage Network or Hiyaa Flats

A total of 6720 units have been allocated for housing in the Hiyaa Flats in Hulhumale Phase Two. Utility work in the site is being conducted by State Electric Company for electricity and Maldives Water and Sewerage Company Pvt Ltd for water.  
 
STELCO has yesterday announced that they have completed work on energizing the Medium Voltage Network at the site. The 18 transformers in the site are now LIVE too and are ready for the connection of the low voltage cables to be connected from the individual towers. This phase of the work is being carried out by a China-based company.  
 
Agreement signing of the Hiyaa Flats are scheduled to be underway from later this month onwards, but unless the cable connections are completed, units will not have electricity for usage. STELCO informs that work is ongoing with hopes of not delaying the process beyond this month.